LesaffreYeast Factory

STEP conducted complete modernization of the production complex to accommodate "SAF-NEVA" office, Lesaffre representative office, storage facilities as well as customer training center. Modernization plan for Lesaffre factory called for complete renovation of utility system, installation of new windows, rooftops, and some work on the adjacent territory. In fact, only the main walls remained untouched from the original building structure.
Industry sector
Industrial construction
Location
Saint Petersburg
Customer
Lesaffre
Project duration
30.09.1999 – 30.12.2000
Contract type
General contract on construction