BELAYA GORAGold Mill

Construction project at "Belaya Gora" gold deposit in Khabarovsk Region begun in the winter of 2012 and a year later the first ingot was cast at the new processing facility.
To carry out this project, STEP constructed the main processing building, a tailing dump, boiler room, accommodation camp for 300 people, office building, fuels, lubricants and chemical reagents storage areas, roads, power lines, water treatment and other facilities. This was the first project of its kind for STEP.
Industry sector
Industrial construction
Location
Khabarovskiy Region , Nikolaevsk-on-Amur
Customer
Russdragmet, LLC
Project duration
01.02.2012 – 01.03.2014
Contract type
General contract on construction