Air Separation Unit Construction of a modern Air Separation Unit with a capacity of 2,000 tons of oxygen per day for industrial gas (air separation products) supply (Cherepovets)

The General Contract for construction of an Air Separation Unit (ASU) with a capacity of 2,000 tons of oxygen per day for industrial gas (air separation products) supply in the territory of Severstal metallurgical plant in Cherepovets was concluded with Air Liquide Severstal, AO in October 2019.  

Construction works with the installation of the first bored and cast-in-place pile) began on October 19, 2019. As of November 2019, 80% of the installation of bored and cast-in-place piles outside the existing ASU building №1 was completed. Works on partial dismantling of the existing building wall panels are still in
Industry sector
Industrial construction
Location
Cherepovets
Project duration
19.10.2019 – 30.11.2020
Contract type
General contract on construction